Read JBL ON STAGE 200ID (serv.man3) EMC - CB Certificate online
Ident. Nr.:
98323
Date:
2008-3-11
98323__EMC_TRF
page 37 of 46
13 Voltage dips and interruptions Immunity
13.1 Standard
Basic standard
EN 61000-4-11:2004
Date of testing
2008.2.25
13.2 Measurement equipment
Equipment
Last Calibration
Type
Serial No
.
Manufacturer
Immunity Simulator
February 25,
2008
2008
EMC PRO
SB2617
KEYTEK
13.3 Test set-up
See annex B
The EUT and its load are placed on a table which is 0.8 meter above a metal ground plane measured
1m*1m min. And projected beyond the EUT by at least 0.1m on all sides. The power cord shall be used
the shortest power cord as specified by the manufacturer.
1m*1m min. And projected beyond the EUT by at least 0.1m on all sides. The power cord shall be used
the shortest power cord as specified by the manufacturer.
13.4 Test results
Mode
Table
Remarks
Result
TM1;
TM2
017
>95% reduction 0.5 period :performance criterion B
30% reduction 25 period :performance criterion C
>95% reduction 250 period :performance criterion C
Pass
13.5 Table
13.5.1 Table 017
Environmental
phenomenon
phenomenon
Voltage Dips & Short
Interruptions
Interruptions
% U
T
Duration
(ms)
Phase Angle
Result
>95 10
0
°
Pass
Voltage dips
30 500
0
°
Pass
Voltage
interruptions
interruptions
>95 5000
0
°
Pass
Click on the first or last page to see other ON STAGE 200ID (serv.man3) service manuals if exist.