MX-5500N, MX-6200N, MX-7000N (serv.man33). MX-LCX3 LCT A3-Installation Manual - Sharp Copying Equipment Peripheral (repair manual). Page 7

Read Sharp MX-5500N / MX-6200N / MX-7000N (serv.man33) Peripheral online

MX-7000N  MX-LCX3  3 – 7
Front side
Rear side
2)
Check to confirm that the upper section of the LCC left side is
locked.
After checking, lower the adjuster on the lower section of the
LCC right side until it does not rotate.
Locked state
Adjuster section
- When the upper side is not locked
Raise the adjuster on the lower side of the LCC right side until
the hole shown in the figure below comes at the center, and
check that it is locked.
* If lock is incomplete, when the power switch is turned on, the
message, "Check installation of tray 5" is displayed on the
operation panel.
1)
Check that the right caster section is grounded.
Loosen two screws on the lower side of the LCC right side,
ground the caster on the floor, and tighten the screws.
2)
Installation of the left front cabinet
Engage the pawls of the left front cabinet (Package part No. 5)
with the five square holes in the left front side of the LCC, and
press the left front cabinet and fix with the fixing screw C
(Package part No. 8) (1 pc.).
F
Page of 13
Display

Click on the first or last page to see other MX-5500N / MX-6200N / MX-7000N (serv.man33) service manuals if exist.