S-22KA1E5, S-28KA1E5, S-36KA1E5, S-45KA1E5, S-56KA1E5, S-63KA1E5, S-71KA1E5, S-22YA1E5, S-28YA1E5, S-36YA1E5, S-45YA1E5, S-56YA1E5, S-22NA1E5, S-28NA1E5, S-32NA1E5, S-36NA1E5, S-45NA1E5, S-56NA1E5, S-45MA1E5, S-56MA1E5, S-63MA1E5, S-7 - Panasonic Air Conditioner Service Manual (repair manual). Page 121

Read Panasonic S-22KA1E5 / S-28KA1E5 / S-36KA1E5 / S-45KA1E5 / S-56KA1E5 / S-63KA1E5 / S-71KA1E5 / S-22YA1E5 / S-28YA1E5 / S-36YA1E5 / S-45YA1E5 / S-56YA1E5 / S-22NA1E5 / S-28NA1E5 / S-32NA1E5 / S-36NA1E5 / S-45NA1E5 / S-56NA1E5 / S-45MA1E5 / S-56MA1E5 / S-63MA1E5 / S-7 Service Manual online

121 
11.8.5 
INDOOR UNIT DRAIN PIPING 
x  Drain piping must have down-slope (1/50 to 
1/100); be sure not to provide up-and-down slope 
to prevent reversal flow. 
x  During drain piping connection, be careful not to 
exert extra force on the drain port at the indoor 
unit. 
x  The outside diameter of the drain connection at 
the indoor unit is 16 mm. 
Piping material: Polyvinyl chloride pipe VP-16 and 
pipe fittings.
 
x  Be sure to perform heat insulation on the drain 
piping. 
Heat insulation material: Polyethylene foam with 
thickness more than 8 mm (local supply).
 
 
 
Upward routing
Pipe clamp
Indoor
unit
Trap
Down-slope
11.8.6 HEAT 
INSULATION 
Caution
 
Be sure to perform heat insulation on the drain, liquid and gas piping. Imperfection in heat insulation work leads to water 
leakage. 
 
1.  Use the heat insulation material for the refrigerant piping which has an excellent heat-resistance (over 120°C). 
 
Overlap with heat
insulator for piping.
Indoor
unit
Band
(Accessory)
Heat insulator
for piping
(Local supply)
Heat insulator
(Accessory)
Hose clip (Accessory)
Heat insulator (Local
supply) (The thickness
must be at least 8 mm.)
Flexible hose with
heat insulator
(Accessory)
PVC pipe
(O.D. ø16)
(Local supply)
To be glued
It may be required to take off this part for checking
or servicing the drain up motor. Please do not glue.
Make sure that there is no clearance here.
 
 
2.  Precautions in high humidity circumstance. 
This air conditioner has been tested according to the “JIS Standard Conditions with Mist” and have been 
confirmed that there are no faults. However, if it is operated for a long time in high humid atmosphere (dew point 
temperature: more than 23°C), water drops are liable to fall. In this case, add heat insulation material according 
to the following procedure: 
x  Heat insulation material to be prepared… 
Adiabatic glass wool with thickness 10 to 20 
mm. 
x  Stick glass wool on all air conditioners that are 
located in ceiling atmosphere. 
x  In addition to the normal heat insulation 
(thickness: more than 8 mm) for refrigerant 
piping (gas piping: thick piping) and drain 
piping, add a further of 10 mm to 30 mm 
thickness material. 
 
Pipe down
Indoor
unit
Pipe
Putty
Trap
Incision
Drain pipe
 
 
ސ Put the incision at the trap part of the heat insulator 
(for water drain)
Wall seal 
x  When the outdoor unit is installed on a higher position than the indoor unit, install the trap so as not to instill 
rain water into the wall by transmitting in piping. 
x  Stuff the space among piping, the electric wire, and the drain hose with “Putty” and seal the penetration wall 
hole. 
Make sure that rain water do not instill into the wall. 
 
 
 
 
 
Page of 127
Display

Click on the first or last page to see other S-22KA1E5 / S-28KA1E5 / S-36KA1E5 / S-45KA1E5 / S-56KA1E5 / S-63KA1E5 / S-71KA1E5 / S-22YA1E5 / S-28YA1E5 / S-36YA1E5 / S-45YA1E5 / S-56YA1E5 / S-22NA1E5 / S-28NA1E5 / S-32NA1E5 / S-36NA1E5 / S-45NA1E5 / S-56NA1E5 / S-45MA1E5 / S-56MA1E5 / S-63MA1E5 / S-7 service manuals if exist.