S-22KA1E5, S-28KA1E5, S-36KA1E5, S-45KA1E5, S-56KA1E5, S-63KA1E5, S-71KA1E5, S-22YA1E5, S-28YA1E5, S-36YA1E5, S-45YA1E5, S-56YA1E5, S-22NA1E5, S-28NA1E5, S-32NA1E5, S-36NA1E5, S-45NA1E5, S-56NA1E5, S-45MA1E5, S-56MA1E5, S-63MA1E5, S-7 - Panasonic Air Conditioner Service Manual (repair manual). Page 120

Read Panasonic S-22KA1E5 / S-28KA1E5 / S-36KA1E5 / S-45KA1E5 / S-56KA1E5 / S-63KA1E5 / S-71KA1E5 / S-22YA1E5 / S-28YA1E5 / S-36YA1E5 / S-45YA1E5 / S-56YA1E5 / S-22NA1E5 / S-28NA1E5 / S-32NA1E5 / S-36NA1E5 / S-45NA1E5 / S-56NA1E5 / S-45MA1E5 / S-56MA1E5 / S-63MA1E5 / S-7 Service Manual online

120 
INSTALLATION OF DUCT 
1.  There are three ways to install the duct for the air inlet as shown below; (a) ~ (c). 
 
 
 
2.  The bottom of the panel can be converted into an air inlet [as the case of diagram (c)] as shown below; 
 
 
11.8.4 REFRIGERANT 
PIPING 
Refrigerant is charged to the outdoor unit. For details, see the manual for installation work of outdoor unit. (Additional 
charging, etc.) 
 
1.  Brazing for piping. 
a.  Execute brazing before tightening the flare nut. 
b.  Brazing must be executed while blowing 
nitrogen gas. (This prevents generation of 
oxidized scale in copper pipe.) 
2.  When there is a lot of brazings for long piping, 
install a strainer midway of the piping. (The 
strainer is locally supplied.) 
3.  Use clean copper pipe with inner wall surface free 
from mist and dust. Blow nitrogen gas or air to 
blow off dust in the pipe before connection. 
4.  Form the piping according to its routing. Avoid 
bending and bending back the same piping point 
more than three times. (This will result in 
hardening of the pipe). 
5.  After deforming the pipe, align centers of the 
union fitting of the indoor unit and the piping, and 
tighten them firmly with wrenches. 
6.  Connect pipe to the service valve or ball valve 
which is located below the outdoor unit. 
7.  After completed the piping connection, be sure to 
check if there is gas leakage in indoor and 
outdoor connection. 
 
Union
round mark
 
 
x  Confirm the round mark of the union (thin side) is 
always at lower direction after connecting piping. 
 
 
 
 
Vacuum drying 
After completing the piping connection, execute vacuum drying for the connecting piping and the indoor unit. 
The vacuum drying must be carried out by using the service ports of both the liquid and gas side valves. 
 
CAUTION   Use two wrenches and tighten with regular torque. 
Flare nut fastening torque N•m (kgf•cm) 
 
Cooling capacity 
Liquid piping 
Gas piping 
ø6.35mm 18 
(180) ø12.7mm 55 
(560)  2.2kW 
6.3kW 
ø6.35mm 
ø12.7mm 
ø9.52mm 
42 (430) 
ø15.88mm 
65 (660) 
 
7.1kW or more 
ø9.52mm 
ø15.88mm 
 
 
 
 
 
Page of 127
Display

Click on the first or last page to see other S-22KA1E5 / S-28KA1E5 / S-36KA1E5 / S-45KA1E5 / S-56KA1E5 / S-63KA1E5 / S-71KA1E5 / S-22YA1E5 / S-28YA1E5 / S-36YA1E5 / S-45YA1E5 / S-56YA1E5 / S-22NA1E5 / S-28NA1E5 / S-32NA1E5 / S-36NA1E5 / S-45NA1E5 / S-56NA1E5 / S-45MA1E5 / S-56MA1E5 / S-63MA1E5 / S-7 service manuals if exist.