8.
When connecting the piping, do not allow air or any substances other than the specified refrigerant to enter the refrigeration
cycle. Otherwise, this may lower the capacity, cause abnormally high pressure in the refrigeration cycle, and possibly result in
explosion and injury.
9.
Thickness of copper pipes used must be more than 0.6 mm. Never use copper pipes thinner than 0.6 mm.
10. It is desirable that the amount of residual oil is less than 40 mg/10 m.
11. Do not modify the length of the power supply cord or use of the extension cord, and do not share the single outlet with other
electrical appliances. Otherwise, it will cause fire or electrical shock.
1.
The equipment must be earthed. It may cause electrical shock if grounding is not perfect.
2.
Do not install the unit at place where leakage of flammable gas may occur. In case gas leaks and accumulates at surrounding
of the unit, it may cause fire. 
3.
Carry out drainage piping as mentioned in installation instructions. If drainage is not perfect, water may enter the room and damage the
furniture. 
4.
Pb free solder has a higher melting point than standard solder; typically the melting point is 50 - 70°F (30 - 40°C) higher. Please use a high
temperature soldering iron. In case of the soldering iron with temperature control, please set it to 700 ± 20°F (370 ± 10°C).
Pb free solder will tend to splash when heated too high (about 1100°F/600°C).
1.
Selection of the installation location. Select an installation location which is rigid and strong enough to support or hold the unit, and select a
location for easy maintenance.
2.
Power supply connection to the conditioner. Connect the power supply cord of the air conditioner to the mains using one of the following 
methods. Power supply point shall be the place where there is ease for access for the power disconnection in case of emergency. 
In some countries, permanent connection of this room air conditioner to the power supply is prohibited.
1. Power supply connection to the receptacle using a power plug. Use an approved power plug with earth pin for the connection to the
socket.
2. Power supply connection to a circuit breaker for the permanent connection. Use an approved circuit breaker for the permanent
connection. It must be a double pole switch with a minimum 3.5 mm contact gap.
3.
Do not release refrigerant during piping work for installation, servicing reinstallation and during repairing a refrigeration parts. Take care of
the liquid refrigerant, it may cause frostbite.
4.
Installation work. It may need two people to carry out the installation work.
5.
Do not install this appliance in a laundry room or other location where water may drip from the ceiling, etc.