5. Removing the power/ballast PWB unit assembly.
5-1. Remove the lock screw from the socket holder (with shorter lead) for the lamp unit 1. Slide sideway and
detach the holder.
5-2. Remove the lock screw from the socket holder (with longer lead) for the lamp unit 2. Slide sideway and detach
the holder.
5-3. Disconnect the connectors from the power/ballast PWB unit assembly.
5-4. Remove the six lock screws from the power/ballast PWB unit assembly. Lift and detach this assembly.
6. Removing the inlet PWB unit assembly.
6-1. Remove the three lock screws from the left-side panel at the inlet PWB unit assembly.
6-2. Disconnect the connectors from the inlet PWB unit assembly.
6-3. Remove the two lock screws from the bottom panel at the inlet PWB unit assembly. Lift and detach this
assembly.
7. Removing the optical mechanism unit.
7-1. Remove the five lock screws from the lamp fan assembly.
7-2. Remove the seven lock screws
from the optical mechanism unit.
Lift and detach this unit.
5-1
5-3
5-3
5-2
7-1
5-4
6-3
(PA)
(EC)
6-1
6-2
7-2
7-1
(BB)
(EA)
(PL)
(F7)
(F6)
7-1
Power/ballast PWB 
unit assembly
Lamp fan assembly
Optical mechanism unit
Left-side panel
Inlet PWB unit assembly
Bottom panel
Page of 19
Display

Click on the first or last page to see other XG-V10XE (serv.man8) service manuals if exist.